2015 11 18 Duck Creek Certified Closure Plan Ash Pond No. 1.pdf

Subject: 2015
Title: 2015 11 18 Duck Creek Certified Closure Plan Ash Pond No. 1.pdf
Date: Wednesday, November 25, 2015
   
Summary: Duck Creek closure plan for CCR Unit - Ash Pond No. 1
   

2015 11 18 Duck Creek Certified Closure Plan Ash Pond No. 2.pdf

Subject: 2015
Title: 2015 11 18 Duck Creek Certified Closure Plan Ash Pond No. 2.pdf
Date: Wednesday, November 25, 2015
   
Summary: Duck Creek closure plan for CCR Unit - Ash Pond No. 2
   

2015 11 18 Duck Creek Notice of Availability Closure Plan Ash Pond No. 1 - No 2.pdf

Subject: 2015
Title: 2015 11 18 Duck Creek Notice of Availability Closure Plan Ash Pond No. 1 - No 2.pdf
Date: Wednesday, November 25, 2015
   
Summary: Duck Creek Notice of availability closure plan for CCR units - Ash Pond No. 1 and Ash Pons No. 2
   

2015 Duck Creek CCR Dam Inspection Report

Subject: 2015
Title: 2015 Duck Creek CCR Dam Inspection Report
Date: Friday, February 12, 2016
   
Summary: Dam Inspection Report required by 40 CFR Part 257.83(b)(1) and requirements of 257.73(d) and 257.74(d).
   

2015 Duck Creek Landfill Periodic Inspection

Subject: 2015
Title: 2015 Duck Creek Landfill Periodic Inspection
Date: Wednesday, February 3, 2016
   
Summary: (b)(1) Existing and new CCR landfills and any lateral expansion of a CCR landfill must be inspected on a periodic basis by a qualified professional engineer to ensure that the design, construction, operation, and maintenance of the CCR unit is consistent with recognized and generally accepted good engineering standards. The inspection must, at a minimum, include: (i) A review of available information regarding the status and condition of the CCR unit, including, but not limited to, files available in the operating record (e.g., the results of inspections by a qualified person, and results of previous annual inspections); and (ii) A visual inspection of the CCR unit to identify signs of distress or malfunction of the CCR unit.
   

Duck Creek Power Station CCR Fugitive Dust Control Plan

Subject: 2015
Title: Duck Creek Power Station CCR Fugitive Dust Control Plan
Date: Tuesday, November 17, 2015
   
Summary: Duck Creek Power Station CCR Fugitive Dust Control Plan

2016 Duck Creek Annual CCR Landfill Inspection

Subject: 2016
Title: 2016 Duck Creek Annual CCR Landfill Inspection
Date: Wednesday, January 18, 2017
   
Summary: 2016 Duck Creek Annual CCR Landfill Inspection
   

2016 Duck Creek CCR Annual Dam Inspection Report Ash Pond No 1

Subject: 2016
Title: 2016 Duck Creek CCR Annual Dam Inspection Report Ash Pond No 1
Date: Wednesday, February 15, 2017
   
Summary: 2016 Duck Creek CCR Annual Dam Inspection Report Ash Pond No 1
   

2016 Duck Creek CCR Annual Dam Inspection Report Ash Pond No 2

Subject: 2016
Title: 2016 Duck Creek CCR Annual Dam Inspection Report Ash Pond No 2
Date: Wednesday, February 15, 2017
   
Summary: 2016 Duck Creek CCR Annual Dam Inspection Report Ash Pond No 2
   

2016 Duck Creek CCR Annual Dam Inspection Report Bottom Ash Basin

Subject: 2016
Title: 2016 Duck Creek CCR Annual Dam Inspection Report Bottom Ash Basin
Date: Wednesday, February 15, 2017
   
Summary: 2016 Duck Creek CCR Annual Dam Inspection Report Bottom Ash Basin
   

2016 Duck Creek CCR Annual Dam Inspection Report GMF Pond

Subject: 2016
Title: 2016 Duck Creek CCR Annual Dam Inspection Report GMF Pond
Date: Wednesday, February 15, 2017
   
Summary: 2016 Duck Creek CCR Annual Dam Inspection Report GMF Pond
   

2016 Duck Creek CCR Fugitive Dust Control Annual Report

Subject: 2016
Title: 2016 Duck Creek CCR Fugitive Dust Control Annual Report
Date: Thursday, December 8, 2016
   
Summary: 2016 Duck Creek CCR Fugitive Dust Control Annual Report
   

Ash Pond No. 1 Closure Plan

Subject: 2016
Title: Ash Pond No. 1 Closure Plan
Date: Thursday, November 10, 2016
   
Summary: Ash Pond No. 1 Closure Plan
   

Ash Pond No. 1 Post-Closure Plan

Subject: 2016
Title: Ash Pond No. 1 Post-Closure Plan
Date: Thursday, November 10, 2016
   
Summary: Ash Pond No. 1 Post-Closure Plan
   

Ash Pond No. 2 Closure Plan

Subject: 2016
Title: Ash Pond No. 2 Closure Plan
Date: Thursday, November 10, 2016
   
Summary: Ash Pond No. 2 Closure Plan
   

Ash Pond No. 2 Post-Closure Plan

Subject: 2016
Title: Ash Pond No. 2 Post-Closure Plan
Date: Thursday, November 10, 2016
   
Summary: Ash Pond No. 2 Post-Closure Plan
   

Bottom Ash Basin Closure Plan

Subject: 2016
Title: Bottom Ash Basin Closure Plan
Date: Thursday, November 10, 2016
   
Summary: Bottom Ash Basin Closure Plan
   

Bottom Ash Basin Inflow Design and Flood Control System Plan

Subject: 2016
Title: Bottom Ash Basin Inflow Design and Flood Control System Plan
Date: Thursday, November 10, 2016
   
Summary: Bottom Ash Basin Inflow Design and Flood Control System Plan
   

Bottom Ash Basin Liner Evaluation

Subject: 2016
Title: Bottom Ash Basin Liner Evaluation
Date: Thursday, November 10, 2016
   
Summary: Bottom Ash Basin Liner Evaluation
   

Bottom Ash Basin Safety Factor Assessment

Subject: 2016
Title: Bottom Ash Basin Safety Factor Assessment
Date: Thursday, November 10, 2016
   
Summary: Bottom Ash Basin Safety Factor Assessment
   

Bottom Ash Basin Structural Stability Assessment

Subject: 2016
Title: Bottom Ash Basin Structural Stability Assessment
Date: Thursday, November 10, 2016
   
Summary: Bottom Ash Basin Structural Stability Assessment
   

CCR Landfill Closure and Post-Closure Plan

Subject: 2016
Title: CCR Landfill Closure and Post-Closure Plan
Date: Thursday, November 10, 2016
   
Summary: CCR Landfill Closure and Post-Closure Plan
   

CCR Landfill Run-on and Run-off Control System Plan

Subject: 2016
Title: CCR Landfill Run-on and Run-off Control System Plan
Date: Thursday, November 10, 2016
   
Summary: CCR Landfill Run-on and Run-off Control System Plan
   

Duck Creek CCR Notice of Availability

Subject: 2016
Title: Duck Creek CCR Notice of Availability
Date: Monday, November 14, 2016
   
Summary: Duck Creek CCR Notice of Availability
   

GMF Pond Closure Plan

Subject: 2016
Title: GMF Pond Closure Plan
Date: Thursday, November 10, 2016
   
Summary: GMF Pond Closure Plan
   

GMF Pond Hazard Potential Assessment

Subject: 2016
Title: GMF Pond Hazard Potential Assessment
Date: Thursday, November 10, 2016
   
Summary: GMF Pond Hazard Potential Assessment
   

GMF Pond Inflow Design and Flood Control System Plan

Subject: 2016
Title: GMF Pond Inflow Design and Flood Control System Plan
Date: Thursday, November 10, 2016
   
Summary: GMF Pond Inflow Design and Flood Control System Plan
   

GMF Pond Liner Evaluation

Subject: 2016
Title: GMF Pond Liner Evaluation
Date: Thursday, November 10, 2016
   
Summary: GMF Pond Liner Evaluation
   

GMF Pond Post-Closure Plan

Subject: 2016
Title: GMF Pond Post-Closure Plan
Date: Thursday, November 10, 2016
   
Summary: GMF Pond Post-Closure Plan
   

GMF Pond Safety Factor Assessment

Subject: 2016
Title: GMF Pond Safety Factor Assessment
Date: Thursday, November 10, 2016
   
Summary: GMF Pond Safety Factor Assessment
   

GMF Pond Structural Stability Assessment

Subject: 2016
Title: GMF Pond Structural Stability Assessment
Date: Thursday, November 10, 2016
   
Summary: GMF Pond Structural Stability Assessment
   

History of Construction

Subject: 2016
Title: History of Construction
Date: Thursday, November 10, 2016
   
Summary: History of Construction

2017 10 17 Duck Creek CCR Bottom Ash Basin Monitoring System Certification Letter

Subject: 2017
Title: 2017 10 17 Duck Creek CCR Bottom Ash Basin Monitoring System Certification Letter
Date: Tuesday, November 7, 2017
   
Summary: 2017 10 17 Duck Creek CCR Bottom Ash Basin Monitoring System Certification Letter
   

2017 10 17 Duck Creek CCR Bottom Ash Basin Statistical Plan Certification

Subject: 2017
Title: 2017 10 17 Duck Creek CCR Bottom Ash Basin Statistical Plan Certification
Date: Tuesday, November 7, 2017
   
Summary: 2017 10 17 Duck Creek CCR Bottom Ash Basin Statistical Plan Certification
   

2017 10 17 Duck Creek CCR GMF Pond Monitoring System Certification Letter

Subject: 2017
Title: 2017 10 17 Duck Creek CCR GMF Pond Monitoring System Certification Letter
Date: Tuesday, November 7, 2017
   
Summary: 2017 10 17 Duck Creek CCR GMF Pond Monitoring System Certification Letter
   

2017 10 17 Duck Creek CCR GMF Pond Statistical Plan Certification

Subject: 2017
Title: 2017 10 17 Duck Creek CCR GMF Pond Statistical Plan Certification
Date: Tuesday, November 7, 2017
   
Summary: 2017 10 17 Duck Creek CCR GMF Pond Statistical Plan Certification
   

2017 10 17 Duck Creek CCR Landfill Monitoring System Certification Letter

Subject: 2017
Title: 2017 10 17 Duck Creek CCR Landfill Monitoring System Certification Letter
Date: Tuesday, November 7, 2017
   
Summary: 2017 10 17 Duck Creek CCR Landfill Monitoring System Certification Letter
   

2017 10 17 Duck Creek CCR Landfill Statistical Plan Certification

Subject: 2017
Title: 2017 10 17 Duck Creek CCR Landfill Statistical Plan Certification
Date: Tuesday, November 7, 2017
   
Summary: 2017 10 17 Duck Creek CCR Landfill Statistical Plan Certification
   

2017 Duck Creek CCR Annual Fugitive Dust Control Report

Subject: 2017
Title: 2017 Duck Creek CCR Annual Fugitive Dust Control Report
Date: Monday, December 11, 2017
   
Summary: 2017 Duck Creek CCR Annual Fugitive Dust Control Report
   

2017 Duck Creek CCR Annual Landfill Inspection

Subject: 2017
Title: 2017 Duck Creek CCR Annual Landfill Inspection
Date: Wednesday, December 20, 2017
   
Summary: 2017 Duck Creek CCR Annual Landfill Inspection
   

2017 Duck Creek CCR Ash Pond 1 Dam Summary Report

Subject: 2017
Title: 2017 Duck Creek CCR Ash Pond 1 Dam Summary Report
Date: Thursday, February 15, 2018
   
Summary: 2017 Duck Creek CCR Ash Pond 1 Dam Summary Report
   

2017 Duck Creek CCR Ash Pond 2 Dam Summary Report

Subject: 2017
Title: 2017 Duck Creek CCR Ash Pond 2 Dam Summary Report
Date: Thursday, February 15, 2018
   
Summary: 2017 Duck Creek CCR Ash Pond 2 Dam Summary Report
   

2017 Duck Creek CCR Bottom Ash Basin Annual Groundwater Monitoring and Corrective Action Report

Subject: 2017
Title: 2017 Duck Creek CCR Bottom Ash Basin Annual Groundwater Monitoring and Corrective Action Report
Date: Tuesday, February 27, 2018
   
Summary: 2017 Duck Creek CCR Bottom Ash Basin Annual Groundwater Monitoring and Corrective Action Report
   

2017 Duck Creek CCR Bottom Ash Pond Dam Summary Report

Subject: 2017
Title: 2017 Duck Creek CCR Bottom Ash Pond Dam Summary Report
Date: Thursday, February 15, 2018
   
Summary: 2017 Duck Creek CCR Bottom Ash Pond Dam Summary Report
   

2017 Duck Creek CCR GMF Dam Summary Report

Subject: 2017
Title: 2017 Duck Creek CCR GMF Dam Summary Report
Date: Thursday, February 15, 2018
   
Summary: 2017 Duck Creek CCR GMF Dam Summary Report
   

2017 Duck Creek CCR GMF Pond Annual Groundwater Monitoring and Corrective Action Report

Subject: 2017
Title: 2017 Duck Creek CCR GMF Pond Annual Groundwater Monitoring and Corrective Action Report
Date: Tuesday, February 27, 2018
   
Summary: 2017 Duck Creek CCR GMF Pond Annual Groundwater Monitoring and Corrective Action Report
   

2017 Duck Creek CCR Landfill Annual Groundwater Monitoring and Corrective Action Report

Subject: 2017
Title: 2017 Duck Creek CCR Landfill Annual Groundwater Monitoring and Corrective Action Report
Date: Tuesday, February 27, 2018
   
Summary: 2017 Duck Creek CCR Landfill Annual Groundwater Monitoring and Corrective Action Report
   

2017 Duck Creek CCR Surface Impoundment EAP

Subject: 2017
Title: 2017 Duck Creek CCR Surface Impoundment EAP
Date: Monday, May 1, 2017
   
Summary: 2017 Duck Creek CCR Surface Impoundment EAP
   

Duck Creek CCR Bottom Ash Basin

Subject: 2017
Title: Duck Creek CCR Bottom Ash Basin
Date: Wednesday, February 8, 2017
   
Summary: Duck Creek CCR Bottom Ash Basin

There are currently no documents that match the criteria.